| :: EU-FIRE Project > Work Package List
| Work package no. |
Work package title |
Lead contractor no. |
Person- months |
Start month |
End month |
Deliverable no. |
| WP1 |
User Requirements and Scenario Definition |
ADAI |
15 |
sep-06 |
ago-09 |
D1, D2, D3 |
| WP2 |
System Requirement Definition |
UCY |
24 |
nov-06 |
ago-09 |
D4 |
| WP3 |
System Design |
DAPP |
38 |
mar-07 |
ago-07 |
D11, D12 |
| WP4 |
Optoelectronic Piloting Unit Development |
DAPP |
20 |
sep-07 |
apr-08 |
D13, D14, D15, D16, D17 |
| WP5 |
Volumetric Acoustic System Development |
BKSV |
45 |
jun-07 |
apr-08 |
D18, D19, D20 |
| WP6 |
Local Control Unit Integration |
DAPP |
14 |
mar-08 |
ago-08 |
D27, D28 |
| WP7 |
System Integration and Validation |
CIRA |
30 |
sep-08 |
dic-08 |
D3, D29, D30, D31 |
| WP8 |
Field Testing |
ADAI |
40 |
apr-07 |
ago-09 |
D38, D39 |
| WP9 |
Project Management and Project Reporting |
DAPP |
13 |
sep-06 |
ago-09 |
D5, D6, D7, D8, D9, D10, D21, D22, D23, D24, D25,
D26, D32, D33, D34, D35, D36, D37, D40, D41, D42, D43, D44, D45, D46, D47 |
|
TOTAL |
|
239 |
|
|
|
|
|
|
|
|
|
|
|