| Milestone No. |
Due Date |
Brief Description
of Milestone objectives |
Decision criteria for assessment |
Date
|
| M1 |
0 |
Kick-Off Meeting |
- |
08/09/2006 |
| M2 |
6 |
System Requirement Review |
Agreement
on preliminary user and system requirements specification |
27/03/2007 |
| M3 |
12 |
System Design Review |
Agreement
on system design report |
15/10/2007 |
| M4 |
12 |
Annual Review First Year |
Successful
agreement and review of first year formal contractual documents |
16/10/2007 |
| M5 |
18 |
Preliminary Development Review |
Agreement
on subsystem requirements and design |
18/03/2008 |
| M6 |
24 |
Critical Development Review |
Agreement
on subsystem integration & validation and acceptance of subsystem prototypes |
04/11/2008 |
| M7 |
24 |
Annual Review Second Year |
Successful
agreement and review of second year formal contractual documents |
05/11/2008 |
| M8 |
28 |
System Integration Review |
Acceptance of EU-FIRE integrated prototype and acceptance of integration and
validation report |
|
| M9 |
36 |
Annual Review Third Year |
Successful agreement and review of third year formal contractual documents |
|
| M10 |
36 |
Final Project Review |
Successful completion of on-site testing, and multi-sensor monitoring
platforms added value assessmentSuccessful agreement and review of final formal contractual
documents |
|