Del no.

Deliverable name

WP no.

Lead participant

Estimated person-months

Nature

Dissemination level

Delivery date (project month)

Status

D1

User Requirements Specification

1

ADAI

9

Re

PU

28/02/07

Issue 1.0 delivered (available in the Download Area)

D2

Scenarios and Fire Model Specifications

1

ADAI

5

Re

CO

28/02/07

Issue 1.0 delivered

D3

Preliminary System Validation Plan

1

DAPP

1

Re

PU

29/05/07

Issue 1.0 delivered (available in the Download Area)

D4

System Requirements Specification

2

UCY

24

Re

CO

28/02/07

Issue 1.0 delivered
D5 First Year Report

9

DAPP

-

Re

CO

04/01/07 Issue 1.0 delivered
D6 First Year Publishable Report

9

DAPP

-

Re

CO

09/01/08 Issue 1.0 delivered (available in the Download Area)

D7

User and System
Requirements Specification

3

ADAI

5

Re

CO

04/10/07

Issue 1.0 delivered

D8

System Design Report

3

DAPP

33

Re

CO

16/01/08

Issue 1.0 delivered

D9

Optoelectronic Piloting Unit
Design & Development Report

4

DAPP

5

Re

CO

26/09/08

Issue 1.0 delivered

D10

Fibre Optic Sensor Network
Design & Development Report

4

DAPP

5

Re

CO

26/09/08

Issue 1.0 delivered

D11

Methodology Guidelines for Optoelectronic Units Design & Development

4

UCY

2

Re

PU

26/09/08

Issue 1.0 delivered (available in the Download Area)

D12

Optoelectronic Piloting Unit
Integrated Prototype

4

DAPP

4

Pr

CO

26/09/08

Issue 1.0 delivered

D13

Fibre Optic Sensor Network
Integrated Prototypes

4

DAPP

4

Pr

CO

26/09/08

Issue 1.0 delivered

D14

Volumetric Acoustic System Design & Development Report

5

CIRA

20

Re

CO

26/09/08

Issue 1.0 delivered

D15

Methodology Guidelines for Acoustic Units Design and Development

5

DAPP

5

Re

PU

26/09/08

Issue 1.0 delivered (available in the Download Area)

D16

Volumetric Acoustic System Integrated Prototype

5

BKSV

20

Pr

CO

30/11/08

 
D17 Second Year Report

9

DAPP

-

Re

CO

13/10/08

Issue 1.0 delivered
D18 Second Year Publishable Report   DAPP - Re PU

13/10/08

Issue 1.0 delivered (available in the Download Area)

D19

Local Supervisor Prototype

6

DAPP

7

Pr

CO

26/09/08

Issue 1.0 delivered

D20

Local Control Unit Prototype

6

DAPP

7

Pr

CO

26/09/08

Issue 1.0 delivered

D21

System Validation Plan

7

DAPP

5

Re

CO

31/12/08

 

D22

EU-FIRE Integration and Validation Report

7

DAPP

15

Re

CO

31/12/08

 

D23

Methodology Guidelines for
Complex Systems Validation

7

DAPP

2

Re

PU

31/12/08

 

D24

EU-FIRE Integrated Demonstrator

7

CIRA

10

De

PU

31/12/08

 

D27

On-Site Testing Results and
System Performance Report

8

ADAI

34

Re

PU

31/08/09

 

D28

Evaluation and Impact
Assessment Report

8

ADAI

6

Re

PU

31/08/09

 
D29 Management and Progress Reports

9

DAPP

-

Re

PU

31/08/09

 
D30 Final Plan for Using and Disseminating the Knowledge 9 DAPP - Re

CO

31/08/09

 

D31

EU-FIRE System Handbook

9

DAPP

-

Re

PU

31/08/09

 